APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

‘Indian power plants need coal within specific range’

17 Jul 2014

July 17: The boilers of thermal power plants in India are normally designed for a certain range of coal quality and require using coal within the above range for satisfactory performance even as performance of power turbines are not affected by change in coal quality, Coal Minister Piyush Goyal has said.

Replying a query in Parliament, Goyal said, “Due to wide variations in the quality of domestic coal generally received by Indian power stations, because of progressive deterioration in coal quality and/or supply from different mines; the boilers are designed to use a wide variation in coal quality, typically from 3,000 to 4,000 kcal/kg gross heat value.”

Thus, the boilers are generally seen to accommodate blend of domestic and imported coal, he said.

However, the quantity or percentage of imported coal that can be blended in any station would depend on a number of factors like the design for the boiler, characteristics of domestic coal being received by the station and characteristics of imported coal proposed for blending, Goyal said.

He further said the two coals are also required to be compatible for blending so as to avoid slagging and other operational problems.