APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

Adani rejigs Australia coal mine budget due to delays

25 Jun 2015

Adani Mining said on Wednesday it was re-jigging the budget on the A$10 billion ($7.72 billion) Carmichael coal mine project in Australia as it faces delays in government approvals.

Adani intends to ship most of the coal from the mine to India for use in generating household power in line with Prime Minister Narendra Modi’s goal to connect all of India to the electricity grid during his tenure.

In announcing the setback, Adani also confirmed a media report that it had asked independent contracting firms employed on the project to halt work around the mine.

 A report in the Guardian Australia said it had asked its four engineering contractors to stop operating, raising speculation that the Indian company might scrap the project altogether.

“This is only temporary,” Adani spokeswoman Kate Haddan said, adding a target to commence coal mining in 2017 stood for now.

Adani in a statement said the project’s current budget based on previous anticipated approval timelines and milestones was no longer achievable due to delays in receiving various approvals from the Queensland state government.

“As a result of changes to a range of approvals over that time, it’s necessary to synchronise our budget, project timelines, and spending to meet those changes,” it said.

Adani has signed up buyers for about 70 per cent of the 40 million tonnes of coal to be produced by the Carmichael project in the first phase.

Adani’s project mainly hinges on environmental approval to deepen a port on the fringe of Australia’s Great Barrier Reef in order to ship the coal, a proposal generating opposition worldwide.

An earlier plan to dump three million cubic metres of soil dredged at the port of Abbot Point into the sea about 25 km (15 miles) from the Great Barrier Reef was rejected.

The Australian federal government must approve the actual channel dredging, and the state needs to clear Adani’s solution for storing the spoil.

A draft U.N. ruling has recommended against listing the Great Barrier Reef as ‘in danger’ but indicated it remains on its watch list ahead of a final ruling due by the end of this month as it monitors plans for dredging.

Eleven of the world’s biggest private investment banks, including Citigroup, Morgan Stanley, Goldman Sachs, and JP Morgan Chase, have publicly ruled out providing financing to Adani, citing environmental concerns over the reef and fossil fuel development.

The Queensland Department of State Development, which is charged with approving the storage procedure, did not immediately respond to a request for comment.

Australia’s Minister for Industry and Science, Ian Macfarlane, recently said he was confident Adani would build the mine because India was looking for a stable supplier of coal.