APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

CIL Feb overburden removal beats target by 24%

02 Mar 2016

In February 2016, CIL achieved 107.79 mn cum of overburden removal (OBR), against the target of 87.01 mn cum, the data showed. Hence, CIL surpassed OB removal target by 24%. The OB removal in February 2016 was, however, 4.93% lower compared to the previous month’s OB removal of 113.39 mn cum.

 

Total OBR during the first 11 months of 2015-16 stood at 483.18 million cubic meters (cum), which was 97.09% compared to the target of 497.62 mn cum set for the period

 

To maintain a growth rate of 10% in coal production, the company is required to increase its OB growth rate by at least 10%, but currently its OB removal is much higher and this augurs well for the company, a former chairman of the company told ICMW.