Indian power sector’s capacity addition at 700 MW in Jan

26 Feb 2014

February 26: India’s power generation capacity addition in January 2014 stood at 700 MW against 1,765 MW recorded during the previous month, according to provisional data of the Central Electricity Authority (CEA).

With this, the total installed generation capacity of the country stood at 234,601.94 MW as on January 31, 2014 while the same was at 233,929.94 MW during the last day of the previous month, revealed the data.

In January 2014, the capacity-addition target was 910 MW for the thermal sector against which the achievement was 700 MW while for the hydro sector the target stood at 68.67 MW against which achievement stood at nil. Target and achievement for the nuclear sector both stood at nil, as per CEA data.

During the month of January, thermal power capacity addition took place only at Rajpura TPP, U-1 (700 MW) in Punjab by Nabha Power Development Limited.

However, during the month of December, thermal power capacity addition took place at Niwari TPP, U-1 (45 MW) in Maharashtra, by BLA Pvt Ltd; Sasan TPP, U#2 (660 MW) in Madhya Pradesh, by Reliance Power; Kawai TPPS St-II, U# 2 (660 MW) in Bihar, by Adani Power; Satpura TPS Extn. U-11 by MPPGCL (250MW); and Tuticorin Indbarath TPP U-2 (150 MW) by Indbarath Ltd.

On the other hand, hydro power capacity was added in December at Nimmo Bazgo HE Project U-1 (15 MW) in Jammu & Kashmir by NHPC and Uri-II, HE , U-2 (60 MW) in Jammu & Kashmir by NHPC. 

Following is the break-up of monthly capacity addition during FY’14, FY’13 and FY’12 (in MW):

Months

2013-14

2012-13

2011-12

April

282

1760

735

May

1570

1070#

550

June

660

2376

2224

July

0

950

1660

August

921

550

1200

September

1365

870

786.5

October

530

1400

345

November

1635

803

2807

December

1765

15

1158

January

 700

877

895

February

 

2863.8

972

March

 

7028

5482*

Total

9428

20562.8

18814.5*

*As reported by CEA, the capacity for 2011-12 was increased by it to 20,501.70 MW instead of 18,814.50 MW.

# CEA had earlier reported that capacity addition in May (2012-13) was 1,070 MW, but it appears that the figures have been revised to 1,130 MW.

## As per the consolidated data provided by CEA, total capacity added during April-March, 2013 stood at 20,622.80 MW although individual month’s capacity addition figure shows the total April-March figure to be 20,562.8 MW.