APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

Land, EC issues make Rs 20-cr projects non-starters at CIL

24 Jul 2014

July 24: Piyush Goyal, Minister of State for Power, Coal & New and Renewable Energy (Independent Charge) said in a written reply to a question in the Lok Sabha on July 24 that a total of 20 coal projects, costing Rs 20 crore and above, could not be started due to constraints relating to land acquisition and environmental clearances at Coal India Limited and its subsidiary companies.

Most of these projects fall in the states of Jharkhand, Maharashtra and Chhattisgarh.

The details of these projects are given below:

Sl.
No

Name of Projects

Estimated
Capacity
(Mty)

State

Status

Likely year of Start
of Production

1

Konar OC, CCL

3.50

Jharkhand

FC granted on 23.10.12. Delay in release of forest land.

2014-15

2

Magadh OC, CCL

20.00

Jharkhand

Delay in possession of acquired land.

2014-15

3

Parej East, UG, CCL

0.51

Jharkhand

Delay in forestry clearance.

2016-17

4

Yekona I OC, WCL

0.40

Maharashtra

Delay in physical possession of tenancy land.

2016-17

5

Penganga OC, WCL

3.00

Maharashtra

Delay in land acquisition.

2016-17

6

Makardhokra I OC, WCL

1.00

Maharashtra

Delay in physical possession of land.

2014-15

7

Singori, WCL

0.80

Maharashtra

Delay in FC & possession of land.

2016-17

8

Yekona-II, WCL

0.60

Maharashtra

Delay in physical possession of tenancy land.

2016-17

9

Bhanegaon OC, WCL

0.60

Maharashtra

Delay in physical possession of land.

2014-15

10

Pauni II OC, WCL

0.60

Maharashtra

Delay in physical possession of land.

2016-17

11

Saraipali OC, SECL

1.40

Chattisgarh

Delay in physical possession of land.

2014-15

12

Bijari OC, SECL

1.50

Chattisgarh

Delay in land acquisition & EC.

Production likely to start beyond XII Plan

13

Ambika OC, SECL

1.00

Chattisgarh

Delay in land acquisition, FC & EC.

2016-17

14

Binkara UG, SECL

0.36

Chattisgarh

Delay in possession of land.

2016-17

15

Jagannathpur OC, SECL

3.00

Chattisgarh

Delay in land acquisition.

2016-17

16

Kartali East OC, SECL

2.50

Chattisgarh

Delay in land acquisition and EC.

2016-17

17

Ketki UG, SECL

0.42

Chattisgarh

Delay in FC.

2014-15

18

Natraj UG, MCL

0.64

Odisha

Delay in FC.

2016-17

19

Pelma Expn OC, SECL

10.00

Chattisgarh

Delay in possession of land.

Production likely to start beyond XII Plan

20

Narainkuri UG, ECL

0.54

WB

Delay  in Env. clearance.