Land, EC issues make Rs 20-cr projects non-starters at CIL
24 Jul 2014
July 24: Piyush Goyal, Minister of State for Power, Coal & New and Renewable Energy (Independent Charge) said in a written reply to a question in the Lok Sabha on July 24 that a total of 20 coal projects, costing Rs 20 crore and above, could not be started due to constraints relating to land acquisition and environmental clearances at Coal India Limited and its subsidiary companies.
Most of these projects fall in the states of Jharkhand, Maharashtra and Chhattisgarh.
The details of these projects are given below:
Sl.
No |
Name of Projects |
Estimated |
State |
Status |
Likely year of Start |
1 |
Konar OC, CCL |
3.50 |
Jharkhand |
FC granted on 23.10.12. Delay in release of forest land. |
2014-15 |
2 |
Magadh OC, CCL |
20.00 |
Jharkhand |
Delay in possession of acquired land. |
2014-15 |
3 |
Parej East, UG, CCL |
0.51 |
Jharkhand |
Delay in forestry clearance. |
2016-17 |
4 |
Yekona I OC, WCL |
0.40 |
Maharashtra |
Delay in physical possession of tenancy land. |
2016-17 |
5 |
Penganga OC, WCL |
3.00 |
Maharashtra |
Delay in land acquisition. |
2016-17 |
6 |
Makardhokra I OC, WCL |
1.00 |
Maharashtra |
Delay in physical possession of land. |
2014-15 |
7 |
Singori, WCL |
0.80 |
Maharashtra |
Delay in FC & possession of land. |
2016-17 |
8 |
Yekona-II, WCL |
0.60 |
Maharashtra |
Delay in physical possession of tenancy land. |
2016-17 |
9 |
Bhanegaon OC, WCL |
0.60 |
Maharashtra |
Delay in physical possession of land. |
2014-15 |
10 |
Pauni II OC, WCL |
0.60 |
Maharashtra |
Delay in physical possession of land. |
2016-17 |
11 |
Saraipali OC, SECL |
1.40 |
Chattisgarh |
Delay in physical possession of land. |
2014-15 |
12 |
Bijari OC, SECL |
1.50 |
Chattisgarh |
Delay in land acquisition & EC. |
Production likely to start beyond XII Plan |
13 |
Ambika OC, SECL |
1.00 |
Chattisgarh |
Delay in land acquisition, FC & EC. |
2016-17 |
14 |
Binkara UG, SECL |
0.36 |
Chattisgarh |
Delay in possession of land. |
2016-17 |
15 |
Jagannathpur OC, SECL |
3.00 |
Chattisgarh |
Delay in land acquisition. |
2016-17 |
16 |
Kartali East OC, SECL |
2.50 |
Chattisgarh |
Delay in land acquisition and EC. |
2016-17 |
17 |
Ketki UG, SECL |
0.42 |
Chattisgarh |
Delay in FC. |
2014-15 |
18 |
Natraj UG, MCL |
0.64 |
Odisha |
Delay in FC. |
2016-17 |
19 |
Pelma Expn OC, SECL |
10.00 |
Chattisgarh |
Delay in possession of land. |
Production likely to start beyond XII Plan |
20 |
Narainkuri UG, ECL |
0.54 |
WB |
Delay in Env. clearance. |
Production likely to start beyond XII Plan |