APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

New facility at Bruce Mansfield power plant to process coal byproduct

15 Oct 2015

Workers have been constructing a new facility to process byproducts from FirstEnergy Corp.'s coal-fired power plant as the company makes a major change in how it disposes of industrial waste.

roject ready for use at the end of 2016. That’s when FirstEnergy has agreed to halt the use of the residual waste impoundment known as Little Blue Run, which many neighbors alleged has  leaked hazardous waste and released noxious odors.

When the Bruce Mansfield plant removes sulfur dioxide from its emissions, it creates coal combustion byproducts. FirstEnergy has been depositing much of that byproduct in Little Blue Run, which straddles Greene Township and Hancock County, West Virginia.

But the state Department of Environmental Protection sued in 2012 over leaks and threats to groundwater because of the impoundment. As part of a settlement, the company agreed to no longer use Little Blue Run by the end of 2016.

Little Blue Run has been the disposal site for Bruce Mansfield since 1974, before any requirement that the impoundment be lined. But James Fitzgerald, manager of major projects, said new disposal sites for materials treated by the new dewatering facility will be different.

“That landfill will have different regulations, different requirements. There are liners associated with it. So it’s a whole different process,” Fitzgerald said.

With the new facility, FirstEnergy will process 2.5 million to 3.5 million tons of byproduct each year, officials said. That byproduct consists of fly ash, sulfur and lime, a chemical used as part of a scrubbing process to address sulfur dioxide emissions, spokeswoman Stephanie Walton said.

The byproduct will be processed at the new facility, where water will be removed, officials said. The water from the process will then be reused at the plant, said Jim Graf, director of the Bruce Mansfield plant.

Once the new facility processes byproduct, it would be moved by barge to another site, but the company is still exploring where those materials could be deposited, Walton said. Those options have included a mine in LaBelle, Fayette County, and a disposal site at Hatfield's Ferry Power Station, also in Fayette County.

The new project will cost more than $200 million, Walton said in an email, and Fitzgerald said the company has about 135 workers at the construction site so far. He said that number of workers could later double.

Some of the plant’s byproduct is already sold and reused by another company that’s right next to the Bruce Mansfield plant. The company, National Gypsum, takes about half a million tons of byproduct each year, using it as material in wallboard, FirstEnergy officials said.

Fitzgerald said the new facility could be mostly completed in summer 2016, and testing could be complete in November of that year.

source: http://www.timesonline.com