APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

No deadline for Dallirajhara-Raoghat-Jagdalpur line

12 Dec 2014

December 12: There is no target for completion of the Dallirajhara-Raoghat-Jagdalpur railway line that is expected to improve iron ore movement significantly due to various reasons, including extreme law and order situation, an official from the Ministry of Railways said.

“The target for completion of the Dallirajhara-Raoght section (95 km) has not been fixed due to non-availability of encumbrance-free land, forestry clearance and extreme law and order situation,” the official said.

“No time-frame can be set at present for completion of the section,” the official added.

The Dallirajhara-Raoghat-Jagdalpur new line project was included in the Railway Budget of 1995-96 but, since then, nothing much has moved on the ground.

The official, however, said, “In the 33 km length, out of a total 95 km, forestry clearance has been obtained and earthwork has been taken up in the first 17 km.”

Meanwhile, regular meetings have been held between the Ministry of Home Affairs, Ministry of Railways and the state government of Chhattisgarh for deployment of necessary forces to facilitate progress of the construction work.