APMDC Suliyari coal upcoming auction 1,00,000 MT for MP MSME on 1st Oct 2024 / 1st Nov 2024 & 2nd Dec 2024 @ SBP INR 2516/- per MT

APMDC Suliyari coal upcoming auction 75,000 MT for Pan India Open on 15th Oct 2024 / 15th Nov 2024 & 16th Dec 2024 @ SBP INR 3000/- per MT

Notice regarding Bidder Demo of CIL Tranche VII STEEL-Coking SUB-SECTOR of NRS Linkage e-Auction scheduled on 19.09.2024 from 12:30 P.M. to 1:30 P.M. in Coaljunction portal

Login Register Contact Us
Welcome to Linkage e-Auctions Welcome to Coal Trading Portal Welcome to APMDC Suliyari Coal

Coal news and updates

SCCL to re-tender for Kakatiya longwall project

15 Oct 2014

October 15: The Kakatiya longwall underground project of Singareni Collieries Company Ltd (SCCL) is going to be delayed as the company will go for re-tendering to appoint a technology provider-cum-operator (TPO).

“The tender for the TPO has been withdrawn and we are going for re-tendering,” a company official told ICMW.

He said workers are currently engaged in “peripheral work” at the project, but progress will start only after the re-tendering process is over.

“As it stands now, I think it will take at least three years for the project to start production,” the official said.

Earlier, the Kakatiya longwall project was expected to start operations from 2015-16.

The project is slated to have a peak production volume of 2.747 million tons per annum (mtpa).