Thermal projects worth 84781 MW capacity facing difficulties: Minister
16 Dec 2014
December 16: A large number of coal-fired power projects with total generation potential of 84,781 MW are facing difficulties, including land acquisition related issues, and are held up or delayed, Power Minister Piyush Goyal has said.
In addition, a total of 5349 MW of gas fired projects in three states of Maharashtra, Andhra Pradesh and Uttarakhand are ready for commissioning but could not start operation due to non-availability of gas, the minister said.
These projects are spread over 16 states and are planned to be ready either in the 12th Plan or beyond, he said.
Of the total projects held up or delayed, 44,600 MW are to be set up by private sector companies, 16,851 MW by Central sector companies like DVC and NTPC and 15,410 MW by State government companies, Goyal said.
Two other Ultra Mega Power Projects (UMPPs) – one each in Jharkhand and Andhra Pradesh – with combined generation capacity of 7960 MW and to be set up by Reliance Power are also held up at present, he said.
Of the total held up or delayed projects, 12290 MW is in Chhattisgarh, 11220 MW in Andhra Pradesh, 9150 MW in Bihar, 9140 MW in Maharashtra, 6780 MW in Uttar Pradesh, 6740 MW in Jharkhand, 5820 MW in Madhya Pradesh, 4720 MW in Odisha, 4700 MW in Karnataka, 4440 MW in Punjab, 3520 MW in West Bengal, 2510 MW in Tamil Nadu, 1800 MW in Telengana, 1000 MW in Gujarat, 850 MW in Assam and 101 MW in Tripura.
Following table provides a state wise and sector wise list of thermal power projects which are under implementation and are due for commissioning in 12th Plan or beyond and are facing difficulties including land acquisition issues along with their anticipated commissioning schedule:
Details of Thermal Power Projects under implementation and due for commissioning in 12th Plan & beyond |
||||||
State |
Project Name |
Unit No. |
Capacity (MW) |
Anticipated Commissioning Schedule |
Issues |
|
Assam |
Central Sector |
|||||
Bongaigaon TPP |
U-1 |
250 |
Jun-15 |
Frequent bandhs, Heavy monsoon and slow civil works. Delay in supply of material by BHEL. Work came to halt due to violence and mass exodus of labour from site in 2011-12. Civil works got affected due to poor performance by civil contractors resulting in to their contract cancellation. Acquisition of balance land for Railway siding. |
||
|
U-2 |
250 |
16-17 |
|
||
|
U-3 |
250 |
16-17 |
|
||
State Sector |
||||||
Namrup CCGT |
GT |
70 |
Sep-15 |
Delay in start and slow progress of civil works, Termination of civil contractor. Poor soil conditions and heavy monsoon. Delay in supply of material by BHEL & shortage of skilled manpower. Termination of NBPL order. Delay in re-award of civil and Mechanical Electrical & Instrumentation agency. |
||
|
ST |
30 |
Dec-15 |
|
||
Sub Total |
|
850 |
|
|
||
Andhra Pradesh |
State Sector |
|||||
Damodaram Sanjeevaiah TPS |
U-2 |
800 |
Jan-15 |
Due to delay in start of civil works and delay in supplies. Delay in readiness of external CHP, RWPH and CT. Delay in readiness of transmission line. Work for transmission line from plant to LILO point is held up due to ROW problem. |
||
Rayalseema TPP St-III |
U-6 |
600 |
Dec-16 |
Delay in start & completion of civil works and land acquisition. |
||
Private Sector |
||||||
Bhavanapadu TPP Ph-I |
U-1 |
660 |
Mar-17 |
Work remained under suspension due to MoE&F order for a long time. After restart works hampered due to two cyclones . Agitation against State bifurcation. |
||
|
U-2 |
660 |
Oct-17 |
|
||
NCC TPP |
U-1 |
660 |
Apr-16 |
Delay in start and slow progress of civil works. Delay in supply & erection of material due to financial problem. |
||
|
U-2 |
660 |
Aug-16 |
|
||
Painampuram TPP |
U-1 |
660 |
Dec-14 |
Delay in start of TG civil work. Delay because of change in foundation design due to soil issue. |
||
|
U-2 |
660 |
Mar-15 |
|
||
Simhapuri Energy Pvt. Ltd Ph-II |
U-4 |
150 |
Jan-15 |
Delay in commissioning of phase-I of the project and delay in supply of TG, CHP, refractory material and MS diffuser. |
||
Thamminapatnam TPP stage -II |
U-3 |
350 |
Aug-16 |
Slow progress of Civil works. Due to financial problem, work at site remained closed for a long time. |
||
U-4 |
350 |
Nov-16 |
|
|||
Vizag TPP |
U-1 |
525 |
Mar-15 |
Delay in readiness of transmission line for start up power. Slow progress of civil works, sea water intake and outfall system, CHP etc.. Delay in readiness of railway line. Delay due to damage because of cyclone. Acquisition of balance land for railway line. |
||
|
U-2 |
525 |
Aug-15 |
|
||
UMPP |
|
|
|
|
||
Krishnapatnam UMPP (Coastal Andhra Power Limited-CAPL) |
U- 1 to 6 |
3960 |
13th plan |
APSPDCL vide letter dated 15.3.2012 has issued termination notice to CAPL stating that in view of the defaults and anticipatory breach having no alternative, the procurers together decided and elect to terminate the agreement and same shall come into effect from 7th day of receipt of this notice. CAPL approached the High Court of Delhi. APSPDCL vide letter dated 20.4.2012 informed that procurers filed counter affidavit on 16.4.2012. The Delhi High Court has dismissed the petition of CAPL on 2.7.2012. CAPL has approached Division Bench, Delhi High Court as well as Indian Arbitrator Council for Arbitration. Developer has also filed petition before CERC. Matter has been kept in abeyance by ICA till disposal of HC petition CERC on 06.06.2013 directed the matter to be listed after hearing in the Delhi High Court. |
||
Sub Total |
|
11220 |
|
|
||
Bihar |
Central Sector |
|||||
Barh STPP- I |
U-1 |
660 |
17-18 |
Delay due to dispute of NTPC with Power machine & Technopromexport, Russia. *Orig. Sch. was in 2009-10 & 2010-11. Delay in supply of boiler material and ordering of Bought out Items(BOIs)by M/s TPE due to financial constraint . Slow progress of works at site by M/s TPE and M/s Powermachines, Russia. |
||
|
U-2 |
660 |
17-18 |
|
||
|
U-3 |
660 |
18-19 |
|
||
Barh STPP-II |
U-5 |
660 |
Mar-15 |
Delay in Supplies by BHEL. Delay in readiness of CHP and Completion of T-23 welding joints. |
||
Muzaffarpur TPS Exp |
U-3 |
195 |
Mar-15 |
Delay in award of main plant civil works. Delay in completion of civil works. Delay in land acquisition & availability of Right of Approach.(ROA) for Raw Water Line. Delay in readiness of CHP , AHP and switch yard. Land acquisition for raw water pipeline & availability of Right of Approach (ROA). |
||
|
U-4 |
195 |
Sep-15 |
|
||
Nabi Nagar TPP |
U-1 |
250 |
Sep-15 |
Delay in acquisition of Land. Slow progress of works by main plant civil agency M/s ERA resulting in delay in handing over civil fronts to erection agencies. Supply of equipment by BHEL. Agitation by villagers. Patches of land could not be acquired because of unwillingness of people to accept compensation. Financial crunch faced by CHP vendor(Techpro). |
||
|
U-2 |
250 |
Mar-16 |
|
||
|
U-3 |
250 |
Sep-16 |
|
||
|
U-4 |
250 |
Apr-17 |
|
||
New Nabi Nagar TPP |
U-1 |
660 |
Jun-17 |
Acquisition of balance land and relocation of homestead owners still living inside the project area. |
||
|
U-2 |
660 |
Sep-17 |
|
||
|
U-3 |
660 |
Jan-18 |
|
||
State Sector |
||||||
Barauni TPS Extn. |
U-1 |
250 |
Oct-15 |
Delay in readiness of CT, CW system etc. Delay in acquisition of land for ash dyke and raw water system. |
||
|
U-2 |
250 |
Dec-15 |
|
||
Private Sector |
|
|
|
|
||
Jas Infra. TPS |
U-1 |
660 |
13th plan |
No work is going on at site. |
||
|
U-2 |
660 |
13th plan |
|
||
|
U-3 |
660 |
13th plan |
|
||
|
U-4 |
660 |
13th plan |
|
||
Sub Total |
|
9150 |
|
|
||
Chhattisgarh |
State Sector |
|||||
Marwa TPP |
U-2 |
500 |
Mar-15 |
Initial delay is due to Change of award of Chimney. Delay in readiness of BOPs (CHP, AHP & 400 KV Switchyard etc.,) and Law & Order Problems, pilferage of material etc. Shortage of man power. |
||
Private Sector |
||||||
Akaltara TPP (Naiyara) |
U-3 |
600 |
Nov-15 |
Shortage of manpower, agitation by Villagers, supply of material due to shortage of fund. |
||
|
U-4 |
600 |
Jul-16 |
|
||
|
U-5 |
600 |
Dec-16 |
|
||
|
U-6 |
600 |
Apr-17 |
|
||
Baradarha TPP |
U-2 |
600 |
Mar-15 |
Delay in Readiness of CHP & AHP, mills. Delay due to problem faced in Generator Stator. Delay in supply of cannibalized/ missing items. |
||
Balco TPP |
U-1 |
300 |
Apr-15 |
Collapse of chimney. Delay in issuing consent to operate by the State Govt. |
||
|
U-2 |
300 |
Jun-15 |
|
||
Bandakhar TPP |
U-1 |
300 |
Feb-15 |
Delay in start of civil works. Work suffered due to financial problems. Delay in readiness of CHP / AHP and problem in generator stator. |
||
Binjkote TPP |
U-1 |
300 |
Jun-15 |
Delay in start of civil works. Delay in supply of the Boiler Drum. Delay due to stoppage of erection work for boiler & TG because of change of STG erection agencies. Balance Land acquisition for ash dyke. |
||
|
|
U-2 |
300 |
Sep-15 |
Delay in start of civil works. Slow progress of pressure parts erection. Balance Land acquisition for ash dyke. |
|
|
U-3 |
300 |
17-18 |
Work yet to start. |
||
|
U-4 |
300 |
17-18 |
Work yet to start. |
||
Lanco Amarkantak TPP-II |
U-3 |
660 |
17-18 |
Delay in acquisition of land for water system. Presently No work is going at site due to financial problems. |
||
|
U-4 |
660 |
17-18 |
|
||
Raikheda TPP |
U-1 |
685 |
Jan-15 |
Delay in start of civil works. Progress of various activities suffered some time due to financial problems. |
||
|
U-2 |
685 |
Jul-15 |
|
||
Singhitarai TPP |
U-1 |
600 |
Dec-15 |
Delay in land acquisition. Slow progress of Boiler & TG erection. Delay due to financial problems. |
||
|
U-2 |
600 |
Jun-16 |
|
||
Swastic TPP |
U-1 |
25 |
Mar-15 |
Delay in readiness of BoPs. Delay due to commercial dispute with CHP vendors & refractory work and defect in super heater coil. Delay in getting Start up power due to transfer of the land of 132 Kv pooling sub station from CSIDC to CSPTCL. |
||
TRN Energy TPP |
U-1 |
300 |
Jul-15 |
Delay in start of civil works. Slow progress in erection works of boiler and T.G. Manpower shortage. |
||
|
U-2 |
300 |
Dec-15 |
|
||
Uchpinda TPP |
U-1 |
360 |
Apr-15 |
Work suffered due to agitation by villagers. Slow progress of work at site. Delay in readiness of BOPs. Delay in readiness of start up power. Delay due to financial problem. Balance land acquisition for ash pond and railway siding |
||
|
U-2 |
360 |
Jun-15 |
|
||
|
U-3 |
360 |
Sep-15 |
|
||
|
U-4 |
360 |
Mar-16 |
|
||
Salora TPP |
U-2 |
135 |
Mar-15 |
Delay in commissioning of unit-1. Agitation by villagers at site. Delay in supply of BTG and CHP material. Non cooperation of BTG supplier in commissioning activities. |
||
Visa TPP |
U-1 |
600 |
17-18 |
Order for AHP, Fire protection system, AC & Ventilation system, LT/HT Switchgear, Cables, Air Compressor, LT transformer, Station transformer, GT & Unit transformer not yet placed. Acquiring of land for Railway siding is pending. Lease deed for 67 acres land. Work is on hold due to financial crunch. |
||
Sub Total |
|
12290 |
|
|
||
Gujarat |
State Sector |
|||||
Sikka TPP Extn. |
U-3 |
250 |
Mar-15 |
Delay in readiness of civil fronts and placement of BOPs Orders. Slow progress of erection of boiler & TG. Slow progress in BoPs. Change of BTG erection agency. Delay in supply of material by BHEL. Shortage of HP welders. |
||
U-4 |
250 |
Jun-15 |
|
|||
Bhavnagar CFBC TPP |
U-1 |
250 |
Mar-15 |
Delay in civil works and non - sequential supply. Slow progress of BoPs. Delay in readiness of AHP and Lignite handling plant. |
||
|
U-2 |
250 |
Jun-15 |
|
||
Sub Total |
|
1000 |
|
|
||
Jharkhand |
Central Sector |
|||||
Bokaro TPS "A" Exp. |
U-1 |
500 |
Sep-15 |
Delay in supply of material by BHEL Delay in handing over of fronts to BHEL because of delay in shifting of switch yard and removal of under ground facilities. Delay in resolution of price variation issues. Readiness of CHP. |
||
Private Sector |
||||||
Matrishri Usha TPP Ph-I |
U-1 |
270 |
17-18 |
Law and order problem. Delay in supply of BTG equipment. Delay in readiness of transmission line due to forest clearance. Work held up due to financial problems since Nov, 12. |
||
|
U-2 |
270 |
17-18 |
|
||
Matrishri Usha TPP Ph-II |
U-3 |
270 |
18-19 |
Law and order problem and delay in supply of BTG material. Work is held up due to financial problems at site . May slip to 13th plan. |
||
|
U-4 |
270 |
18-19 |
|
||
Tori TPP |
U-1 |
600 |
Apr-17 |
Law and order problem. Delay in start of civil work & slow progress of works. Delay in MOEF clearance for Unit-2. |
||
|
U-2 |
600 |
Oct-17 |
|
||
UMPP |
|
|
|
|
||
Tilaiya UMPP |
U-1 to 6 |
3960 |
13th plan |
Land acquisition and preliminary works under process |
||
Sub Total |
|
6740 |
|
|
||
Karnataka |
Central Sector |
|||||
Kudgi STPP Ph-I |
U-1 |
800 |
May-16 |
Delay in award of SG civil works. Delay in TG erection start. Stoppage of work on account of NGT order in 03/14. Unrest and violent agitation in 07/14 with exodus of manpower. |
||
|
U-2 |
800 |
Aug-16 |
|
||
|
U-3 |
800 |
Dec-16 |
|
||
State Sector |
||||||
Bellary TPS |
U-3 |
700 |
Nov-15 |
Delay in awarding civil contract for main plant and BoPs. Delay in awarding of CHP & AHP. Dispute between AHP vendor and BHEL. Delay in supply of L.P. Rotor. |
||
Yermarus TPP |
U-1 |
800 |
Jul-15 |
Repeated soil investigations due to change in plot plan and additional soil investigation at specific areas and IIIrd party vetting. |
||
|
U-2 |
800 |
Nov-15 |
|
||
Sub Total |
|
4700 |
|
|
||
Maharashtra |
State Sector |
|||||
Chandrapur TPS |
U-8 |
500 |
Mar-15 |
Delay in placement of BoPs order and delay in main plant equipment supply. Delay in readiness of BoPs and Heavy monsoon. |
||
|
U-9 |
500 |
Jul-15 |
|
||
|
Koradi TPP Expn. |
U-8 |
660 |
>
Mar-15 |
Delay in civil works. Delays in work progress due to heavy rain. Delay in readiness of BoPs ( Cooling tower, AHP, CHP etc.) by M/s Lanco Infratech due to financial crunch. |
|
|
U-9 |
660 |
Jul-15 |
|
||
|
U-10 |
660 |
Feb-16 |
|
||
Parli TPP Expn. |
U-8 |
250 |
Mar-15 |
Delay in BTG supply. Delay in approval of drawings. Slow erection work. Slow progress in BoPs. Commercial dispute with M/s Sunil Hitech. |
||
Private Sector |
||||||
Amravati TPP Ph-I |
U-3 |
270 |
Feb-15 |
Non-sequential supply of BTG material. Delay in readiness of Civil Fronts. Payment issue with BHEL. Delay in insulation application. Delay in readiness of HFO, CHP &AHP. Re-awarding of boiler erection agency. Readiness of railway siding. |
||
|
U-4 |
270 |
Jun-15 |
|
||
|
U-5 |
270 |
Sep-15 |
|
||
Amravati TPP Ph-II |
U-1 |
270 |
13th plan |
No Work is going on at site due to financial problems. |
||
|
U-2 |
270 |
13th plan |
|
||
|
U-3 |
270 |
13th plan |
|
||
|
U-4 |
270 |
13th plan |
|
||
|
U-5 |
270 |
13th plan |
|
||
Lanco Vidarbha TPP |
U-1 |
660 |
18-19 |
No work is going at site due to financial problems. |
||
|
U-2 |
660 |
18-19 |
|
||
Nasik TPP Ph-I |
U-2 |
270 |
Jan-15 |
Delay in readiness of Railway siding .Non-sequential supply of BTG material & Civil fronts readiness. Payment issue with BHEL. Readiness of Mills, HFO, CHP & AHP, ducting insulation etc. |
||
|
U-3 |
270 |
Jun-16 |
Non-Acceptance of BTG material by Project Authorities. No work is going at site due to financial problems. |
||
|
U-4 |
270 |
Sep-16 |
|
||
|
U-5 |
270 |
Mar-17 |
|
||
Nasik TPP Ph-II |
U-1 |
270 |
13th plan |
No Work is going on at site due to financial problems. May slip to 13th plan. |
||
|
U-2 |
270 |
13th plan |
|
||
|
U-3 |
270 |
13th plan |
|
||
|
U-4 |
270 |
13th plan |
|
||
|
U-5 |
270 |
13th plan |
|
||
Sub Total |
|
9140 |
|
|
||
Madhya Pradesh |
Central Sector |
|||||
Vindhyachal TPP Ph-V |
U-13 |
500 |
Oct-15 |
Delay in placement of BOPs order. Delay in erection of boiler material. |
||
Gadarwara STPP |
U-1 |
800 |
Jun-17 |
Delay in balance land acquisition and ordering of balance BoP's |
||
|
U-2 |
800 |
Nov-17 |
|
||
Private Sector |
||||||
Anuppur TPP Ph-I |
U-1 |
600 |
Jan-15 |
Delay in start and slow progress of civil works. Delay in supply of Drum. Readiness of insulation of boiler and ESP. |
||
|
U-2 |
600 |
Jul-15 |
|
||
Mahan TPP |
U-2 |
600 |
Jun-15 |
Delay in development of Coal Block |
||
Nigri TPP |
U-2 |
660 |
Feb-15 |
Delay in start of civil works. Delay in preparation of ACW system. Delay in readiness of Transmission line. |
||
Gorgi TPP |
U-1 |
660 |
18-19 |
Order for main plant equipment has not been placed so far. |
||
Seoni TPP Ph-I |
U-1 |
600 |
Apr-15 |
Delay in readiness of civil fronts. Chimney readiness. Delay in supply of boiler and TG material due to financial problem. |
||
Sub Total |
|
5820 |
|
|
||
Odisha |
Private Sector |
|||||
Derang TPP |
U-2 |
600 |
Jan-15 |
Delay in commissioning of unit-1.Law and order problem. Delay in land acquisition. Agitation by villagers. |
||
Ind Bharat TPP (Orissa) |
U-1 |
350 |
Mar-15 |
Delay due to heavy rains. Delay in readiness of transmission line for start up power. Acquisition of Balance land of 3 KM which falls in mining area for railway line. |
||
|
U-2 |
350 |
Jun-15 |
|
||
KVK Nilanchal TPP |
U-1 |
350 |
Jun-16 |
Initially delayed due to chimney clearance and law & order problem. Work was held up due to stay by Hon'ble High Court of Orissa. Hon'ble High Court has given order dated : 20.05.14 to start the work. Delay in restart of work. |
||
|
U-2 |
350 |
17-18 |
|
||
|
U-3 |
350 |
17-18 |
|
||
Lanco Babandh TPP |
U-1 |
660 |
17-18 |
Delay in land acquisition. No work is going on at site due to financial problem |
||
|
U-2 |
660 |
17-18 |
|
||
Malibrahmani TPP |
U-1 |
525 |
May-15 |
Delay in land acquisition and delay in supply of TG hall structures. Slow progress due to financial problem. |
||
|
U-2 |
525 |
Dec-15 |
|
||
Sub Total |
|
4720 |
|
|
||
Punjab |
Private Sector |
|||||
Goindwal Sahib |
U-1 |
270 |
Jun-15 |
Delay in readiness of CHP & AHP. Delay in readiness of Railway line. No progress of work at site due to financial problem. |
||
|
U-2 |
270 |
Sep-15 |
|
||
Talwandi Sabo TPP |
|