Almost 50% coal blocks allotted to power PSUs face delay in prodn: Report
19 Sep 2022
Seven out of the total 16 coal
blocks issued to state-owned power sector entities or PSUs like
National Thermal Power Corporation (NTPC), Damodar Valley Corporation (DVC),
Neyveli Lignite Corporation (NLC), THDC (a mini-Ratna company under NTPC) and
Patratu Vidyut Utpadan Nigam Ltd (PVUNL - a joint venture between NTPC and
JBVNL) are yet to start or have just started production, even more than seven
years after their allotment.
This
is despite the fact that coal
blocks were allotted to these power sector PSUs back
in March 2015 to fulfil their shortage of dry fuel, as India's largest coal
producer, Coal India Ltd (CIL), on its own, could not completely meet their
requirements.
Reasons like delay in land acquisition, environment and forest clearances,
non-availability of land records as well as law and order issues are the main
reasons behind lack of work in these coal blocks, sources aware of the
developments said.
According
to sources, of the original 16 coal
blocks allotted to these entities, only five have reached
production stage, while three have applied for surrender and one was
surrendered last month. In the remaining seven blocks, work on coal excavation
is yet to begin or has just begun.
Out
of these seven reserves, four blocks belong to NTPC and PVUNL (NTPC's joint
venture with the Jharkhand Bijli Vitran Nigam Ltd or JBVNL) while the other
three coal reserves belong to the DVC, the NLC, and the THDC.
The
DVC had two blocks, out of which it surrendered Khagra Joydev coal block
situated in West Bengal last month, as land acquisition could not be done for
it, sources privy to developments said.
As
far as the status of these seven blocks is concerned, Power Ministry sources
said that production work in NTPC's Chatti Bariatu coal block in Jharkhand has
only begun in April, while its Kerandari block (Jharkhand) is expected to
become operational by the end of this fiscal.
However
its third reserve Banhardih (also in Jharkhand and owned by its joint venture
PVUNL) is likely to become operational only by 2024-25, as both forest and
environmental clearances are awaited.
The
NTPC's fourth coal block Badam (yet again in Jharkhand) will begin work in
2023-24 as transfer of mining lease as well as stage two of forest clearance is
awaited.
The
DVC's Tubed coal block is also expected to begin operation by end of this
financial year, sources informed, as its forest clearance is expected shortly.
The
NLC's Pachwara South coal reserve in Jharkhand is expected to start production
work next year in 2023-24 as environmental and forest clearances are awaited.
The
THDC's Amelia block in West Bengal is likely to begin work during this fiscal
itself as appointment of mine developer and operator (MDO) is underway.
Sources said that these allottees were expected to draw a standard plan at the
time of allocation itself, in order to get the necessary clearances expedited
and other formalities completed on time. This could have helped commencing
production from these blocks as per schedule and would have gone a long way in
meeting the objective of providing adequate coal supply to power plants.
--IANS