Imported coal-based power plants told to run at full capacity till September
13 Jun 2023
The power ministry on Monday mandated imported
coal-based power plants to run at full capacity till September 30 to meet the
high power demand amidst soaring temperatures across the country. The ministry
had in February directed these plants to run optimally from March 16 to June 15
under Section 11 of the Electricity Act. Monday’s directive effectively extends
this timeline by over three months.
Power demand, though earlier projected to peak
around 229 GW in April, reached 216 GW in the month, and 221 GW in May, thanks
to the turn in weather conditions. However, rising temperatures in the last two
weeks have pushed the demand up. On June 9, India recorded the highest ever peak power demand at 223 GW,
though still lower than the projected peak.
There is also the challenge of monsoon in the
coming months, where domestic coal production and evacuation usually declines, for which
imported coal-based plants can come to the rescue. Section 11 of the
Electricity Act provides that the government may, in extraordinary
circumstances, ask a generating company to operate and maintain any station in
accordance with its directions.