India’s coal approval spree marks change in energy transition strategy: Analysis
08 Aug 2023
New Delhi, Aug 8 (IANS): Close
to 11.5 gigawatts (GW) of coal power capacity under development moved forward
through various approval stages in the first five months of 2023, a new
analysis by Global Energy Monitor (GEM) and the Center for Research on Energy
and Clean Air (CREA) said on Tuesday.
India permitted about 3.9 GW of coal projects and 7.6 GW of coal
projects received terms of reference, moving them one step closer to permits.
Despite the concerning uptick, the number of projects in development
(announced, pre-permit, and permitted coal capacity, including captive and
non-captive) has shrunk by a staggering 85 per cent since 2014, from 250 GW to
36 GW.
“India’s coal approval spree in 2023 marks a change in India’s energy
transition pattern. Last year, India did not approve any new coal power plants
for the grid, which was in line with the global trend of moving away from the
dirty, expensive, and outdated energy,” said GEM research analyst Flora
Champenois.
India is actively developing 65.3 GW of coal power capacity. Of this,
30.4 GW of coal power capacity is under construction and 35 GW is in various
pre-construction phases (14.4 GW permitted, 11.8 GW pre-permitted, and 8.8 GW
announced).
The analysis notes that India’s current proposals overshoot the already
significant coal capacity expansion projected in the country’s energy plan.
Based on five-year projections in India’s latest National Electricity Plan
(NEP 2023), more than 8 GW of non-captive coal-fired power plant capacity in
active construction is unnecessary, and all 34.9 GW of the pre-construction
capacity is also not needed.
Under the NEP’s 10-year coal projections, there is no need for any new projects
to enter the pre-construction pipeline. If all pre-construction coal capacity
was to come online, and 2.1 GW was to retire as projected in the NEP, installed
on-grid coal capacity would reach 275 GW, far exceeding the NEP’s projected
requirement of 259.6 GW in FY2032 under the base case.
Sunil Dahiya from CREA said, “Electricity demand estimated in India’s
National Electricity Plan has always been over-projected compared to real
demand. In the past, this has led to billions of dollars worth of coal power
plants turning into non-performing assets (NPA). The ongoing push for more coal
power proposals already exceeds requirements and therefore could again lead to
more stranded assets.”
He further added, “Going ahead with these projects will not only worsen
financial standing but also lead to climate, air pollution, and health
disasters in the future. Adequate and efficient actions need to be taken now to
avert these disasters.”
India has the opportunity to push for a stronger outcome and accelerate
the global coal to clean energy transition at the G20 leaders’ summit in Delhi
in September, addressing the twin needs of energy access and energy security.
An orderly move towards clean energy will also help confront the climate
crisis, raise economic productivity, create jobs, and improve environmental and
public health outcomes.
Simultaneously investing in both coal and renewables will only result in
a messier energy transition for India.
“The country has the opportunity to set the right example and push for a
strong coal-to-clean outcome at the G20 leaders’ summit in Delhi in September,”
added Champenois.